80 days on; 100 more to completion!

80 days on; 100 more to completion!

The new lobby and reception area gradually taking shape at Level 1 of the new block.

Today marks the 80th day work started on the Nalanda Centre Expansion Project.  As we draw closer to the scheduled half-way point of reconstruction, the building itself is gradually taking a more concrete and complete shape!

Currently, the Nalanda Building Fund is still short of nearly RM700,000.  We would like to appeal for your support to contribute to this noble project to benefit a wider community with many more wholesome programmes in future.  Donations and sponsorships are most welcome in the name of beneficiary – “Nalanda Buddhist Society”.  Thank you and mettā !

A heavy-lift crane was deployed to lift concrete for laying the floor-slab on Level 4.